# Task-plan review: pre-push-safety-net
|
|||
|
|
|
||
|
|
Date: 2026-09-12. Scope: design readiness and implementation task graph, not runtime validation.
|
||
|
|
|
||
|
|
## Authorization and phase
|
||
|
|
|
||
|
|
After the amended requirements/design and JavaScript transfer plan were presented, the maintainer
|
||
|
|
said **"ok, next kiro phase"**. This was applied as approval of those concrete documents for task
|
||
|
|
generation. Requirements/design are approved; generated tasks remain unapproved and implementation
|
||
|
|
has not begun. The initial acceptance profile is an evaluation target, not a demonstrated SLA.
|
||
|
|
|
||
|
|
## Design readiness assessment
|
||
|
|
|
||
|
|
**GO for task generation.** The design retains the existing ranker as scope owner, excludes vendor
|
||
|
|
code from targets/graphs, preserves language-agnostic evidence contracts, and separates graph
|
||
|
|
claims from actionable change-related alerts. Boundaries, integration paths and all 35 numeric
|
||
|
|
requirements have concrete design counterparts. No fundamental design gap was found in this review.
|
||
|
|
|
||
|
|
Three material risks are explicit work and release gates, not assumed solved:
|
||
|
|
|
||
|
|
1. Whole/changed-unit graph cost may not meet the hook deadline: measure the uncached baseline
|
||
|
|
before cache work, then realistic warm edits rather than identical-tip hits alone (5.2, 8.2).
|
||
|
|
2. Frontend/framework or sanitizer semantics may prevent an actionable claim: retain the gap,
|
||
|
|
keep the affected capability experimental, and route new engine work to its owning spec (3.3, 8.3).
|
||
|
|
3. Repeatedly inspected examples do not prove transfer: freeze the core and retain untouched
|
||
|
|
evidence per language/framework/family, with noise/recall/coverage gates together (1.2, 8.3).
|
||
|
|
|
||
|
|
## Independent task-graph sanity review
|
||
|
|
|
||
|
|
Reviewer received the draft task plan and paths to requirements, design, evaluation and task rules,
|
||
|
|
without a parent-generated coverage summary. The first verdict was **NEEDS_FIXES**:
|
||
|
|
|
||
|
|
- Cache reuse can complete more work within the same deadline. Task 6.4 must require evidence/
|
||
|
|
admission equality for the same completed questions; complete-scope equality belongs to a controlled
|
||
|
|
sufficient-budget comparison, not every deadline-limited run.
|
||
|
|
- Requirement 8.1 needs explicit paired normalized PHP/JavaScript contract tests, including equivalent
|
||
|
|
capability eligibility and an unsupported-origin negative control (3.2, 4.2).
|
||
|
|
- A Node holdout cannot admit PHP or Python capabilities. Untouched evaluation is required for each
|
||
|
|
language/framework/family; missing evidence leaves that capability experimental (1.2, 8.3).
|
||
|
|
|
||
|
|
All three were repaired once. The same independent reviewer read the repaired draft and returned
|
||
|
|
**PASS**, with no remaining important task-graph issue. No return to design was required.
|
||
|
|
|
||
|
|
## Mechanical and scope checks
|
||
|
|
|
||
|
|
- Eight major groups and 27 executable subtasks; one parallel candidate (3.1), otherwise sequential
|
||
|
|
because the work shares backend, ranker, cache and integration contracts.
|
||
|
|
- All 35 requirement IDs mapped; every executable subtask has an observable completion condition,
|
||
|
|
responsibility boundary, and valid explicit dependencies where needed.
|
||
|
|
- No task is checked off; no acceptance-critical tests are optional. No deployment is included.
|
||
|
|
- The initial experiment is 5.2; persistent caching follows it. Normal alert eligibility is gated
|
||
|
|
at 8.3, so experimental diagnostics do not become noisy advisory output during development.
|
||
|
|
- Final file/metadata validation and `git diff --check` are the fresh document checks. No runtime
|
||
|
|
code or tests changed, and no graph/performance measurements were rerun during task generation.
|
||
|
|
|
||
|
|
Next phase: human task approval, then implementation starting with group 1.
|